Morson Project Focus | 79 Days in Derby

safety matters derby station
author profile picture

by Jessica Tabinor on

     SAFETY MATTERS | 5 MIN READ

  • We take a look at the £200m, high profile and unique transformation project at Derby train station.

  • The project team had only a 79-day window to complete the work, alongside the added challenge of not closing the station

  • At the project’s peak, around 900 people were on site every day, as well as additional plant and machinery on constant standby to minimise delays in the event of a failure

On Sunday 22 July 2018, work started on the £200m resignalling at Derby, with the project team having a 79-day window to complete the work, alongside the added challenge - for the most part - of not closing the station.

Closing the station and diverting all services away from Derby would have brought severe disruption to commuters travelling throughout the East Midlands, whilst only saving around one week on the overall delivery schedule; therefore, the decision was made to keep as many trains in operation as possible. Only one day in the 79-day blockade saw there be no trains in operation, to provide detailed testing and commissioning of the newly installed signalling.

At the project’s peak, around 900 people were on site every day, as well as additional plant and machinery on constant standby to minimise delays in the event of a failure.

Led by Network Rail, the project involved:

  • Replacing 17km of track and laying 150,000 tonnes of ballast.
  • Installing 79 sets of points, 65 new signals and 10 new signal gantries.
  • Creating one new platform.

The Derby blockade required project track engineers to untangle and simplify the existing layout into the station, which had seen only slight modifications since the Victorian era. A total of eight different track layout options were proposed, with the chosen design resulting in fewer trains being held up outside of the station waiting for a platform, as well as improved journey times by increasing line speeds through the station from 15mph to up to 40 mph through all the Platforms.

The new design also brought significant improvements to rail traffic, with six passenger trains now able to move simultaneously at the London Road Junction, instead of the previous two. The new layout now also allows movements in and out of the station on both the London and Birmingham routes at the same time, something that wasn’t previously possible.search morson jobs Installing a new island platform created two additional platforms at Derby Station: Platform 6 for passenger services, which will primarily be used for London services and includes two new lifts and a First-Class lounge. Platform 7 is to be used as a service platform to collect train crew, whilst providing additional facilities to scale up the station’s capabilities in emergency situations and was used to run London trains from during the works in August. Additional work was also delivered to realign and lengthen platforms 2-5.

Signalling upgrades meant that the station is now controlled from the East Midlands Control Centre in Derby, marking the closure of the Derby Power Signal Box that first opened in 1969.

Maintaining safety throughout a project that sat adjacent to an operational railway was a priority, with physical barriers created, where possible, between worksites and running lines, as well as every staff member being required to carry out a ‘line open to traffic brief’ that explained which lines were open at what times.

July’s month-long heatwave, which saw temperatures soar to more than 30 degrees, also created various issues. Dust suppression units were erected around the station, as the dryness of the ballast created more dust than normal, and all staff operating within the 30m exclusion zone wore mandatory full breathing PPE.

On Monday 8 October 2018, normal train services resumed in and out of Derby Station, making the successful completion of the 79-day transformation.

The project’s overall mission was never to directly increase capacity on the line, despite passenger numbers rising to 3.7m during 2017, but to improve the overall flow of traffic with smoother journeys and less disruption.

The 79-day Blockade has renewed and replaced life-expired equipment, whilst improving the layout to and from Derby by removing a key bottleneck, meaning better journeys for millions of passengers each year and ensuring the station can continue providing future capacity improvements through new trains and additional infrastructure upgrades.

Morson’s involvement

Sub-contracted on behalf of AmeySersa, we supplied numerous Vital Human Resources personnel to the project spanning a range of capacities, from site supervisors, through to crane controllers and track gangs, as well as a number of our Morson Vital Training apprentices. Our involvement began in advance of the blockade, laying the foundations required for the 79-day window, and we are currently still involved in the finishing touches and clean up today.

It was a huge honour to be part of such a high profile and unique project made up of several mini blockades throughout the partial closure. We were one of only two manpower providers delivering the specialist skills needed to complete the £200m project and a huge credit goes out to all our Vital operatives who were involved, with numerous comments on how proud they were to see the project taking shape each day.


Download our latest issue of Safety Matters to read more about everything from health and safety innovation and project wins to top tips and case studies. Or, to search for our latest jobs, click here

safety matters


Cx Jobs

Integrated Support Engineers (AW101/159/LYNX Bulletins)

A leading Aerospace and Defence client based in Yeovil Somerset are recruiting for several Technical Authors/ Intregrated support/ILS/Service Bulletin engineers. Backgrounds from AW101/159/LYNX would we welcomed, ideally with some level of experience of technical publications.The primary role of the Integrated Support Engineer Airworthiness/Bulletins is to support the Principal Engineer Airworthiness and Service Bulletins Co-ordinator in the effective delivery of airworthiness documentation across the business spectrum from our supply base to end customer to ensure corrective actions are controlled and instigated, resulting in formal company airworthiness documentation is issued to ensure LHD in service aircraft fleet is maintained in an airworthy manner .Ensure the work is performed in accordance with departmental procedures DPR.CSU.15.12 KEY JOB ACCOUNTABILITIES%ofTimeEmployees· You are responsible for ensuring that activities under your control are undertaken in accordance with the requirements set out in the AWL SHE Policy, Health & Safety Operating manual, Health, Safety & Environment Management System Manual (HSE MSM). These documents identify your key responsibilities under the Health and Safety at Work Act 1974, Environmental Protection Act and other relevant HS&E legislation.·Specific responsibilities for Employees are detailed within HSE MSM Section 8.7 - Employees Main Activities· Produce Technical Instructions as a consequence of airworthiness data from all areas of the business to manage the correct mitigating actions are controlled to ensure the customer base is informed in a timely manner of all airworthiness information and required corrective actions as appropriate.· Maintain and as required liaise with all stakeholders to successfully close the issuing of aircraft inspections or modification instructions to reduce the cost of ownership of the aircraft, and control the implementation of product enhancements.· Manage your individual activities, its dependencies to ensure completion of the related tasks against priorities from an airworthiness perspective and aircraft delivery, to ensure the LMW fleet is delivered and maintained in an airworthy manner.· Provide and maintain complete workload status reports to ensure performance metrics can be produced.· Support the business with the expert technical process knowledge for the delivery of the correct airworthiness technical information in a timely manner to limit the amount of business exposure. Thus reducing the overall operating costs of the business by ensuring a cost effective solution is promulgated to the customer base, whilst maintaining fleet availability.·Ensure the associated Technical Instructions are developed in accordance with all relevant departmental procedures and company operating system, and ensure any recommendations for continued improvement are highlighted to the management team.· You are responsible for taking reasonable care of your own health and safety and that of others who may be affected by your acts or omissions at work and to co-operate with managers, supervisors and others to enable the company to meet its statutory obligations for health, safety and environment. 10% 90% ESSENTIAL KNOWLEDGE, SKILLS & EXPERIENCEEducated to at least HNC level in a relevant aviation related subject. Alternatively, to have completed a recognized engineering apprenticeship followed by a period of employment in all aspects of aircraft maintenance and overhaul, sufficient to gain the necessary practical experience for the job roleAircraft engineering and/or aircraft Technical Publications experience.Knowledge of Air Publication specifications e.g. ASD Spec 1000D, MilSpec1388 LSAR, DADS, DAvP 70/77, ATA02/90, ATA100, etc. An understanding of Airworthiness and Flight Safety regulations and requirementsKnowledge of technical authoring and production tools e.g. Framemaker, Eagle Publishing System (EPS) and CAPS2000.Good understanding of LMW Helicopter productsExcellent understanding of engineering drawings and use Dassault Enovia, with an understanding of the configuration management system and process.Good inter-personal skills.Keyboard skills, a working knowledge of computers and computer system applications.Written communication skills, the ability to document results from the audits performed and documenting validation reports and plans.Highly self-motivated and able to work as part of an integrated team as well as independently

PMO Lead

Our client BAE Systems Barrow is recruiting Project Support Office Leads to lead a team in achieving programme goals and performance targets. Candidates MUST be proficient userS of EVM tools and techniques. For the foreseeable future this will likely be remote working rather than on site at Barrow. The Project Support Office Lead will be accountable for interpretations of data and information, acting as an enabler in the decision making process.The role involves but is not limited to the following:Work with the Project Control's management team in defining Project Controls Processes/Organisation for the Programme/ Projects.Provide support into Control Account Managers with the most complex accounts to enable effective management of costs, schedule, risks and opportunities and resources across whole Projects.Provide analysis of Earned Value Management (EVM) Data and variance reporting to the CAM populationLead and manage the production of various Project/Programme reports, using a variety of Software/Reporting Techniques and accountable for robust metrics and management reports required for the CAM Review process and CSR Reviews. Provide support, expertise and advice on data analysis and forecasting to Senior Management. Provide expertise in project planning, monitoring and control tools, techniques and procedures to Programme teams and Cost Account Managers.Lead improvement initiatives within the organisation in particular assist in establishing a robust project control culture within the business. Lead on System/Process development and creation, distribution and analysis of ad hoc reports.Accountable for supporting the CAM's in defining the work content of the control account (Statement of work) to support resource estimating. Accountable for providing timely inputs to the Company BRP Process to ensure required resource is available to carry out the defined scope of work. Accountable for analysis and reporting on cost and schedule performance in line with monthly CAM reviews and support completion of arising actions. Ensure integrity of overall Project data.Ensure general governance for all Project Controls processes; including Work Packages [Open/Close/Data Validation etc] at appropriate - authorised level and; regular cost and schedule baseline maintenance and support through the Performance Measurement Baseline Change Request (PMBCR) process. Accountable for production of Programme Information, analysing, identifying and communicating areas for continuous improvement. Lead, develop and motivate any reporting and assigned staff through good communication and honest open management techniques in keeping with company values, policies and procedures and Take responsibility and accountability for the performance management of the team [including PDR's, ESM, performance reviews etc] in line with the company process. Work with Cost Engineering and Finance in the development of accurate estimates in support of bids, annual budgets or cost to completion and analyse "spend to date" data. To be able to access, have a clear understanding of and apply the Quality and HS&E Management System documentation e.g. Process Instructions, Workmanship Standards, Risk Assessments etc. applicable to particular work scope and to obey all HS&E rules.Key Attributes Foundation Degree / HNC / HND / Certificate in Project Management or equivalent level of qualification Highly skilled in the use of Microsoft packages LCM Awareness Proficient user of EVM Tools and TechniquesRecognising the RESTRICTED nature of the work, suitable candidates will be SC cleared or eligible for this level of clearance. SC must be in place before start date.Please do not apply if your experience does not match the job spec above but please visit our website to view other roles.Due to the volume of CVs received if you have not had a response within 48 hours please take it that your application will not be progressed.

Finishing Operative

Looking for 4 finishing operatives able to install: * plasterboard, * a wraptite membrane * and a sealant strip to the inside of a commercial building in SW London

SPC - Site Person in Charge - Rail Construction

Working on a project to replace sidings and increase the number of roads, a civils gang to support the site manager and construction team to ensure that the daily operation and safety of the site is kept correct and in line with the safe systems of work. At times there will be a requirement to assist the track gang in the planned works on site. The majority of these works is planned for Monday to Friday 07:30 to 15:30Essential* Hold ICI-LU Licence* Hold LU Basic Track Awareness(BTA)* Hold Site Person In Charge (SPC)Desirab;e* Previous Experience in construction projects and the construction environment* Previous Experience in working with machinery and on track vehicles* All trained/Competent in Cat Scanning RD 8000* All trained/Competent in Banksman/Slinging* All trained/Competent in working from height* All trained/Competent in Disc Saw & Concrete Saw cutting* All trained/Competent in Belle Mixers/ Concrete Mixing* All Hand Arm Vibration trained* At least 1 No. First Aider* All fully face fitted staff

Austin Distel Va Opp86kf Q Unsplash

Advertisement